Construction of New Slabs at the HLP Plant – APC

Construction of New Slabs at the HLP Plant – APC

Removal of concrete slab, curbs on level of 14 meters from Ground level.

Dismantle of existing centrifuge machines and motors( 8 machines 20Tons each)

Supply & installation of new GFRP reinforcing bars for the slab & curbs.

Supply & placement of concrete for the slab & curbs.

Supply & installation of new supports for existing centrifuge machines & re-setting of existing centrifuge machines, re-routing & connection of existing piping & wiring to machines.

Supply & installation of new protective resinous system on top of the slab & curbs.

Supply & installation of new railing system.


Duration of Contract: 40 days 24/7 during APC 2016 Major Shutdown.

Project Value: 1,232,212 USD

Contract Status: Completed 6th April, 2016, ahead of schedule by two days.

Year Completed:  2016

Location: Dead Sea – Jordan