Deep Well and Filtration Unit – German Jordanian University

Deep Well and Filtration Unit – German Jordanian University

Design, supply and installation of 450 meters Deep Well Pump long with Motor Control Center. Water pumped has been treated by modern smart system (Glass Media Filtration) to reduce turbidity and eliminate high concentration of minerals like iron. The capacity is 360 m3/day.

Treated Water Pumped through lifting station to underground reservoir located 350 meters though under ground HDPE pipeline. 

Produced water has been tested according to Jordanian Standards No. JS-286 and found satisfactory as drinking water.


Project Value: 150,000 USD

Commencement Date: Nov 11, 2012

Substantial Handover Date: Dec 22, 2012

Contract Duration: 60 days

Final Handover Date: Dec 22, 2013

Year Completed:  2013

Location:  Madaba – Jordan