Lajjoun Wells Water Supply Project Pipeline 2

Lajjoun Wells Water Supply Project Pipeline 2

The Lajjoun water supply project was further expanded with the Water Authority of Jordan again appointing ConEx as the contractor for supplying and constructing a 28 km ductile iron transmission pipeline with a diameter of 800 mm from Swaqa to Qastal Pumping Station, in addition to the needed facilities and appurtenances for a value exceeds seven million USD. 


Duration of Contract: 180 Calender Days

Project Value: 7.4 million USD

Year Completed:  2003

Location: Swaqa-Qastal– Jordan