LPG – Filling Station Project (Up gastan)
As a subcontractor for civil works and erection of electromechanical works for the Spanish company Duro Felguro, ConEx completed construction of all facilities and accessories for the LPG Filling Station Project including earthworks, platforms, concrete works, drainage, trenches, landscaping, and steel structure.
Duration of Contract: 720 Calender Days
Project Value: 2.5 million USD
Year Completed: 2002
Location: Amman – Jordan