Restructuring & Rehabilitation of Greater Amman’s Water Supply System

Restructuring & Rehabilitation of Greater Amman’s Water Supply System

Being one of the subcontractors for restructuring and rehabilitation of the greater Amman Water Supply Project (C-15) for the Morganti Group inc., this extensive project under contract by USAID grant, which involved work on secondary distribution system and restructuring works, rehabilitation works and mobilization requirements.

ConEx part entailed installation of pipelines transmission ,values, fire hydrants, water meters, data loggers and miscellaneous works serving the areas of Yasmin, Yadodeh, Um Uthainah and Nazzal within the greater Amman vicinity.

Our installation works of pipelines transmission consisted of 72km D.I.P

(with diameter of 150-1000mm), 135 km HDPE (with diameter of 125mm), 50 km HDPE (with diameter of 25-36mm) and 50 km GIP (with diameter of 15-150mm).

The value of the project undertaken by ConEx exceeds six million USD and the duration is eighteen months.


Year Completed:  2005

LocationAmman – Jordan